Submitted by Angarrack.info ... on Wed, 12/11/2014 - 00:00.
Via http://planning.cornwall.gov.uk/online-applications/applicationDetails.d...
Status: Disch of cond not all conditions agreed
Reference: |
PA14/08363 |
Alternative Reference: |
n/a |
Application Received: |
01 Sep 2014 |
Address: |
South Quay Hayle Cornwall TR |
Proposal: |
Submission of details to discharge conditions 23, 40 and 42 in respect of decision notice PA12/10064 |
Status: |
Disch of cond not all conditions agreed |
Appeal Status: |
|
Appeal Decision: |
|
Ref. No: PA14/08363 | Received date: Mon 01 Sep 2014 | Status: Pending Decision | Case Type: Application 23. No development for any phase shall commence until full details of the hard landscaping works, including phasing proposals for that phase, have been submitted to and approved in writing by the local planning authority and these works shall be implemented in accordance with the approved details and phasing unless otherwise agreed in writing by the local planning authority. The hard landscaping details shall include proposed finished ground levels or contours; means of enclosure; car parking layout; other vehicle and pedestrian access and circulation areas; and hard surfacing materials and finishes, minor artefacts and structures (e.g. furniture, public art, refuse or other storage units, proposed and existing functional services above and below ground (e.g. drainage, power, communications cables, pipelines etc. indicating lines, manholes, supports etc.)
Reason: In the interests of visual amenity and to protect the character and significance of heritage assets in accordance with the aims and objectives of paragraphs 58 and 131 of the National Planning Policy Framework, the saved Policies 1 and 2 of the Cornwall Structure Plan 2004 and policy 7b of the World Heritage Site Management Plan.
40. No phase of development shall commence until a methodology statement for that phase, including a programme of works detailing the extent of the works for the repair and restoration of the quay walls within that phase (if any) has been submitted to and approved in writing by the local planning authority. The development for that phase shall be carried out and thereafter maintained in accordance with the approved details before any of the retail uses within that phase hereby permitted commence or residential dwellings are occupied.
Reason: To ensure the conservation and repair of the historic fabric of these listed quays to ensure the protection of the character of the listed buildings and the authenticity and integrity of the World Heritage Site in accordance with the aims and objectives of paragraph 128 of the National Planning Policy Framework, the saved Cornwall Structure Plan policy 2 and the World Heritage Site Management Plan policy 8a.
42. Before commencement of development, details of the materials, finish and method of construction, including details of the foundation and junction with listed quay walls, of the new quay wall at Carnsew channel and an appraisal of the method of removing this new quay wall shall be submitted to and approved in writing by the local planning authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: To protect the character, fabric and setting of the listed quay walls and to protect the historic character and distinctiveness of the Cornwall and West Devon Mining Landscape World Heritage Site in accordance with the aims and objectives of paragraphs 58 and 131 of the National Planning Policy Framework, the saved Cornwall Structure Plan policy 2 and the World Heritage Site Management Plan policy 8b.
| | 17/09/2014 |
| DISCHARGE OF CONDITION(S) |
Matt Williams
Feilden Clegg Bradley Studios
Bath Brewery
Toll Bridge Road
Bath
BA1 7DE
Your ref:
My ref: PA14/08363
Date: 13 November 2014
Dear Sir/Madam
Submission of details to discharge conditions 23, 40 and 42 in respect of decision
notice PA12/10064 at South Quay, Hayle, Cornwall.
I refer to the details submitted in respect of the above.
I confirm that the details submitted for some of the conditions are acceptable and that you
have satisfied and discharged the following:
Condition Number 23 Discharged on 13 November 2014
Condition Number 42 Discharged on 13 November 2014
The other condition(s) that have not been discharged are listed below:
Condition Number 40
The reason for not discharging this condition is:
Further information required.
This does not relieve you of your obligation to comply with the Building Regulations or with
any condition(s) on the original planning permission.
Yours faithfully
Jeremy Content
Senior Development Officer
Planning and Enterprise Service
Tel: 01209 614064
Planning and Enterprise Service
Cornwall Council
Dolcoath Avenue Camborne Cornwall TR14 8SX
planning@cornwall.gov.uk
PADISZ
Tel: 0300 1234 151
www.cornwall.gov.uk
Recent comments
32 weeks 5 days ago
34 weeks 3 days ago
34 weeks 3 days ago
44 weeks 1 day ago
1 year 4 weeks ago
1 year 29 weeks ago
1 year 39 weeks ago
1 year 51 weeks ago
3 years 23 weeks ago
4 years 8 weeks ago